Prompt Payment on Ontario Construction Projects

How Ontario's prompt payment rules work on larger projects: proper invoices, the owner's 28-day deadline and the notice of non-payment.

CONSTRUCTION

11/17/20264 min read

white concrete building during daytime
white concrete building during daytime

On a high-rise, multi-unit or high-value custom project, cash flow moves through a chain of contracts. Ontario's Construction Act sets statutory deadlines for that money. The prompt payment rules are in Part I.1 of the Act.


Amendments that took effect on January 1, 2026 changed how invoices are treated. This article explains the rules as they read on the current Ontario e-Laws consolidation of the Act.

Which contracts the rules cover

The prompt payment Part does not apply to every contract. It does not apply to a contract entered into before October 1, 2019. Nor does it apply where the owner began the procurement process before that day, or to a subcontract under either kind of contract.


The January 1, 2026 amendments apply to an improvement on and after the day they came into force. Section 87.4 provides exceptions. For an improvement already under way, the amended invoice rules apply on and after January 1, 2026. Contracts that the 2019 transition rule keeps outside Part I.1 stay outside it.

What a "proper invoice" is

The 28-day clock runs from a "proper invoice." The Act defines it as a written bill or other request for payment for services or materials supplied under a contract for an improvement. It must contain the following, and any other requirements the contract specifies:


  • the contractor's name and address;

  • the date of the invoice, and the period, milestone or other contractual payment entitlement it relates to;

  • information identifying the contract or other authorization, such as a contract number, line item or purchase order number;

  • a description of the services or materials supplied, with quantities where appropriate;

  • the amount payable and the payment terms;

  • the payment recipient's name, mailing address and telephone number (and title, if the recipient is a person rather than an office or department);

  • any other information the owner reasonably requests that is necessary for the proper functioning of its accounts payable system; and

  • any other information prescribed by regulation.

Invoices are now deemed proper unless the owner gives notice within seven days

Since January 1, 2026, an invoice that does not meet the requirements of the definition is still deemed to be a proper invoice. The exception is a written notice from the owner, given within seven days after receiving the invoice. It must identify the deficiency and what is required to address it.


For an owner or developer, the first week after an invoice arrives now matters. An incomplete invoice that goes unanswered for seven days is treated as proper.

Monthly invoicing and payment certifiers

Proper invoices are given to the owner monthly, unless the contract provides otherwise. Some contracts make a proper invoice conditional on a payment certifier's prior certification or the owner's prior approval. Such a term has no force or effect.


A contract may still provide for certification or owner approval after a proper invoice is given. The restriction also does not apply to a term providing for testing and commissioning.


The Act modifies this for alternative financing and procurement arrangements. These are project agreements between the Crown, a municipality or a broader public sector organization and a special purpose entity. The agreement requires the entity to finance and undertake the improvement. For those agreements, and the entity's agreement with its contractor, the restriction on prior certification does not apply.


A contractor may revise a proper invoice after giving it, on three conditions. The owner agrees in advance, the invoice date does not change, and the revision still meets the definition. The seven-day deeming rule also applies, with necessary modifications, to a revised invoice.

The owner's 28-day deadline

An owner must pay the amount payable under a proper invoice no later than 28 days after receiving it. That requirement is subject to any holdback the owner must retain under the Act.

The notice of non-payment

An owner who disputes a proper invoice may refuse to pay all or part of it. To do so, the owner must give the contractor a notice of non-payment no later than 14 days after receiving the invoice. The notice must be in the prescribed form and manner. It must state the amount being withheld and detail all of the reasons for non-payment.


Any amount not covered by the notice remains due within the 28 days. The reasons may include amounts retained as a set-off by a trustee or as a lien set-off under the Act.

Payment down the chain

The rules continue below the owner. Suppose a contractor receives full payment of a proper invoice on time. Within seven days, it must pay each subcontractor whose services or materials were in that invoice. This too is subject to the contractor's own notice of non-payment.


If the owner does not pay some or all of the invoice on time, the contractor's obligation to its subcontractors still has a deadline. Subject to a permitted notice of non-payment, the contractor must pay them within 35 days after giving the owner the proper invoice. It covers each included subcontractor's amount payable, to the extent not already paid from a partial payment by the owner.

Interest on late amounts

Interest begins to accrue on any amount that remains unpaid when due under Part I.1. The rate is the prejudgment interest rate under the Courts of Justice Act. If the contract specifies a different rate, the greater of the two applies.

Points to keep in view on a larger project

  • Record the date each invoice is received. The seven-, 14- and 28-day periods run from receipt.

  • Review invoices for completeness on arrival. A deficiency notice comes within seven days, in writing.

  • Check that any certification process in the contract runs after a proper invoice is given, not before.

  • A notice of non-payment must give all of the reasons, in the prescribed form.

General information

This article is general information about Ontario law as of its publication date. It is not legal advice about any project or contract. The outcome of any payment dispute depends on its facts and the contract documents.

Speaking with a lawyer

Wolf Law acts for developers, owners and general contractors on high-rise, multi-unit and high-value residential projects across Ontario. To schedule a consultation, email info@wolflaw.ca.


Schedule a Consultation


Related: Construction law | For developers | For owners


Sources: Construction Act, R.S.O. 1990, c. C.30, Ontario e-Laws, https://www.ontario.ca/laws/statute/90c30

Wolf Law

1563 Dundas St. W., 2nd Floor

Mississauga, ON L5C 1E3

Phone: 1 (833) 963-WOLF (9653)

Local: (905) 739-0616

Fax: (289) 985-0200

Email: info@wolflaw.ca

Wolf Law Professional Corporation. Legal services provided by lawyers licensed by the Law Society of Ontario. The information on this site is general information, not legal advice. Contacting us does not create a lawyer-client relationship.